The first inspection would be earlier than the muse concrete is poured. The second is after framing is completed, plumbing has been “roughed” in and electrical wiring has been run, but earlier than the walls ha
The first inspection would be earlier than the muse concrete is poured. The second is after framing is completed, plumbing has been “roughed” in and electrical wiring has been run, but earlier than the walls ha